Astar inspection and testing services is been Award “CRISP VTB Subsea Pipeline Project” from Mcconnell and ITP JV

VTB Subsea Pipeline across West Jurong Channel for the Chemical and Refining Integrated Singapore Project (CRISP). The pipeline is approximately 1.8 km long that will connect the two COMPANY facilities, JLP at Shipyard Road and the reclaimed land adjacent to the PAC Refinery located on Jurong Island.

The pipeline is Pipe in Pipe section with 18” as the casing pipe and 12” as the carrier pipe, material grade DNV 450 DU. Expected duration of the project is from Mid November 2018 to June 2019.

The Pipeline inspection will by PAUT inspection, welding methods will be by semi auto (FCAW, GTAW).